The Ministry of Health issued an advance payment of $610.631 million to a contractor on December 15, nine days before the contract was signed for a regional accommodation project. Almost a year later, that project has not commenced although the full contract sum of $2.035B has long been processed.
The information is contained in the Report of the Auditor General on the Public Accounts of Guyana for Ministries, Departments and Regions for 2025.
According to the report, a contractor was awarded $2.035 billion for the construction of accommodation in Regions 2, 3, 4, 5, and 6 on December 24, 2025 and by December 31, 2025, the full sum was processed.
“It was discovered that the ministry cut and held cheques for the entire contract sum in 2025, and all cheques were prepared and certified for payment to the contractor nine days before the contract was signed,” a section of the report read.
Additionally, the contractor was issued an advance payment of $610.631 million nine days before the contract was signed.
“To further compound the problem, it was revealed that the ministry certified and approved the full contract sum to be paid to the contractor before the contract was signed. Audit checks revealed that the ministry also certified and approved the remaining balance on the contract sum, an amount of $1.425 billion in four separate payments all on the 15 December 2025, nine days before signing a contract with the contractor,” the report stated.
The Auditor General, Deodat Sharma said physical verification of the sites conducted between May 22, 2025 and June 2026 revealed that land clearing works had commenced at only one of the sites located at Bath Village, Region 5. It was noted, however, that the contractor was not mobilized on the site at the time. Additionally, at the other sites, no work had commenced.
Further, the Auditor General fount that the commencement order dated December 8, 2025 contradicted the Special Conditions of Contracts (SCC), which stipulated a duration of six months for completion upon issuing the commencement order, however, the commencement order stated nine months.
Additionally, the SCC included a defects liability period of four months, while the commencement order stated five months.
“According to the signed contract agreement, the completion date for the works was July 8, 2026, however, our physical verifications revealed that land clearing works have commenced on one site,” the report states.
In response to the series of discrepancies detected by the Auditor General’s office, the Health Ministry explained that it received Cabinet’s approval on November 27, 2025 for the project through sole-source procurement method. However, due to what it described as “administrative oversight” the payment documents were processed.
“The ministry wishes to clarify that these payments were not released to the contractor,” the Health Ministry said, while adding that a typographical error was responsible for the variation in the completion date between the commencement order and the SCC.
It clarified that the contract duration was set at nine months.
“The ministry acknowledged the limited progress made on the project. The works were delayed due to the challenges relating to the availability of suitable land at the original locations. Following a review of the project, policy guidance was given to relocate the accommodation units to the following hinterland hospital locations, where they will better support the operations of the new hospitals upon completion: the Moruca Hospital, Kato Hospital, Bartica Hospital, Kamarang Hospital and Cotton Field,” the Health Ministry stated.
Meanwhile, in the case of the $69.045 million Maternal Waiting Home at Sand Creek, Region Nine, the project remains largely incomplete although approximately $25 million was paid to the contractor as of December 31, 2025.
“Based on physical verification conducted on 7 August 2026, it was revealed that the works were incomplete and there was no active construction works ongoing at the site. At the time, the contractual completion date had already elapsed. Additionally, substandard works were observed in sections of the perimeter beams and columns,” the Auditor General stated.
The Auditor General also found that “poor-quality concrete mix” was used, in addition to savannah sand as against white sand. It was disclosed that some of the beams constructed were grossly deformed and inconsistent in level, and displayed structural cracks due to poor concrete mix utilized.
The Health Ministry, in response, disclosed that the consultancy firm hired to supervised and monitor the project has since had its services terminated, while the contractor was instructed to demolish the existing structure, and reconstruct all defective and non-compliant sections, including the affected beams and columns.