The Parliamentary Committee of Supply today approved a further $24.7 Billion to continue works on the Government’s flagship, gas-to-energy project.
The approved funds will now push the overall project cost to US$956 Million
Facing a mountain of questions from Opposition Members of Parliament today, Prime Minister Mark Phillips said the additional funds is expected to see the project to its conclusion.
He said the contracting company, LYNSACA, had made a request for an additional US$200 million to continue the project, and the Government has so far provided US$130 million and will be making the additional US$70m available.
“Yes we had money budgeted for this year, the money was expended, the project is ongoing, they are cost overrun, we had meetings with the project directors from the company LYNSACA and coming out of that meeting in order not to pause this project, bearing in mind we made a promise to the people of Guyana that we will deliver 300 megawatts of electricity at half the cost, we are behind schedule, we don’t want to go to litigation or anything we want this project to continue to its end and deliver to the promise to the people,” the Prime Minister said.
The Government was hoping to see first fire from the project in December, but the Prime Minister told the the Committee of Supply that start up is now anticipated by the end of the first quarter of 2027.
The project received an original budgetary provision of $10.72 billion and an additional $19 Billion which was previously sought. The Prime Minister said those monies have already been utilized. The new approval now pushes the total cost approved for this year to nearly $55 Billion.

“The money that was allocated was already utilized, this is additional money that we are asking for because we owe it to the people of Guyana to complete this project, no more stalling, pausing or holding up. We made a commitment to the people of Guyana that they will get 300 additional megawatts of power at 50% of what they are paying for now, yes there is a delay, so what? What do you do,” the Prime Minister questioned.
The Prime Minister informed the Assembly that the Government will also be paying for additional legal and consultancy services pertaining to the project.
“The additional cost pertaining to the completion of phase 1, that is the cost we have to pay the contractor Lynsaca who is completing phase 1, and then the expansion, because there is a lead them for the supply of the turbines for phase 2, we took a decision now to find that initial amount of money and pay it down and secure those turbines, so when we go through the process and determine who will construct the work for phase 2, that will start but we are comfortably assured that when they are ready to install the turbines, the turbines are there for Guyana,” the Prime Minister noted.
The Prime Minister said the Government continues to invest in the project because of its intended benefits to Guyanese. He said Government intends to keep its promise to slash electricity costs by half when the project comes fully on stream.