More than three years after the signing of an $870.5 million contract for the construction of the Belle Vue Pump Station in Region 3, the project remains largely incomplete.
With a long history of missed deadlines, the multi-million project, awarded to Tepui Group Inc, is now expected to be completed in May 2027, according to the Auditor General’s 2025 report.
“Our physical verification on 2 September 2026 revealed that the structure was still incomplete and the works were being undertaken by the assigned contracting firm,” a section of the report reads.
The project, which falls under the National Drainage and Irrigation Authority (NDIA), was originally awarded to Tepui Group Inc on August 14, 2023 at the sum of $865.544 million. However, the contract was rescinded and a second award was made on September 15, 2023, this time to the tune of $870.564 million.
The contract was awarded by the National Procurement and Tender Administration Board (NPTAB) against an engineer estimate of $779.199 million despite multiple red flags.
“An examination of the contractor’s bid submissions revealed that the contractor failed to satisfy nine out of 18 requirements set out in the evaluation criteria,” the report states.
The Auditor General Deodat Sharma, in the report, said while no payments were made in 2025, amounts totaling $160.8 million was paid during the prior years.

Originally, the project was expected to be completed within 18 months, however, due to a series of missed deadlines, NPTAB approved an addendum in June 2025, allowing to Tepui Group Inc to enter into an arrangement with another contractor – Gaico Construction and General Services Inc. – to assist with the completion of the project.
“Examination of the work programme submitted indicated an approved completion date of 16 June 2026 and this date has also elapsed. At the time of reporting, the contractor was granted a further extension of time to complete the works, with the new completion date now being 31 May, 2027,” the report states.
The Auditor General expressed concerned that after three years, the project has not advanced significantly.
“At the time of our verifications, three years had already elapsed since the contract was signed and still no significant works have been completed, with excavation and earthworks in progress along with driving of timber piles for the foundation slab of the sluice structure,” the Auditor General said.
It was noted that the foundation for the northern pump station was the only component completed, while construction of reinforced concrete retaining walls to the required level was in progress.
The Auditor General was also keen on pointing out that the advance payment bond remained expired since March 21, 2025 and was never renewed. Additionally, an outstanding sum of $121.7 million or 93% of the mobilization advance payment is still to be recovered.
“The performance bond was also never extended and does not provide the required periods of coverage stipulated in the contract. This situation also is a fundamental breach of contract and should not be tolerated by the ministry,” the Auditor General said.
He said at the time of reporting in September 2026, the project was progressing at an “unacceptably slow pace.”
The Ministry of Agriculture, in response, told the Audit Office that the construction of the pump station is approximately 33% completed. It also rejected the contention that a 30% advance payment was made, explaining that the contractor only received a 15% advance.
Additionally, the Agriculture Ministry said NDIA, in a letter dated April 13, 2026, asked the contractor to renew and extend both the Advance Payment Bond and the Performance Bond.
The Audit Office also found that the construction of two other pump stations – one at A-Line Sluice, West Coast Demerara and another at Pouderoyen – remain largely incomplete due to a number of issues although the contracts for those projects were awarded in 2022 and 2023 respectively.
In light of these challenges, the Auditor Office has urged the Agriculture Ministry to improve its supervision of projects.